Date: 9/30/98
Name of group: Keshav’s Kids
Team members: Bryan Camilli & Ed Weiss
Task: 6. Management & Integration
Brief description of task:
Same as the task specification from the project overview.
Pseudocode:
Control Application / GUI services
Status:
Which hosts are up?
Which calls are going through the gateway?
Which users are available?
Alarms / Indications of parts of the network that go down.
Performance:
Throughput
Response Time
Available Resources
Usage/Workload
Performance History / Degradation of Performance
Network Configuration:
Voice-Packet size
Security Keys
Topology Information
Interfaces that we will use:
Backdoor Hooks and Stubs
Schedule:
Remaining
Weeks:
9 -> Set up software version control software and project file hierarchy. (CVS)
Instruct group members on usage of CVS.
8 -> Review interface specs for all teams to ensure compatibility.
7 -> Integrate bare-bones network with null interfaces from each team.
Begin to install hooks and stubs into telephony components.
6 -> Begin development of GUI
5-1 -> Continued reintegration and testing of network and interfaces between
components.
Continued development of managerial software
What you need from the course staff:
I’m sure we’ll become increasingly needy as the project progresses.
References:
Course Textbook
Course Webpage
Keshav’s Conference
"Internet Telephony: Architecture and Protocols an IETF Perspective" (as
suggested)